						 Title: PM1 Retainage for Atlantic Community High Recommendation: 
I recommend the School Board approve Reduction of Retainage from 5% to 1% for Atlantic Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description:   
Atlantic Community High School – Modernization Project #0862-8206 
  
Description: On Atlantic Community High School, Modernization Project, the Contractor, Centex Rooney Construction, achieved Substantial Completion on August 9, 2005 and requested a Reduction in Retainage from 10% to 5%.  The District staff recommends this reduction.  
Financial Impact: 
The financial impact to the Project's Budget is $0.00.  