Title: PM4 Retainage and Final for Jupiter High Recommendation:
I recommend the School Board approve Reduction of Retainage from 1% to 0%, and approve Final Payment and ratify Final Acceptance for Jupiter Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
Jupiter Community High School – Modernization Project #0081-8220
Description: The Project Architect, MPA Architects, has certified that Jupiter Community High School, under contract with The Morganti Group, achieved Final Completion on January 4, 2005.
The General Contractor has requested, and the Architect and Staff have recommended, Final Payment and Final Acceptance.
- Punch List items were Completed
- Certification of Occupancy was Obtained
- Closeout Documents were Received
- Errors & Omissions did not Exceed 1%
- Final M/WBE Participation Achieved: 26.13%
Financial Impact:
The financial impact to the Project's Budget is $0.00.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
PM4 Backup.pdf
PM4 Site Plan.pdf
PM4 Data Panel.pdf
|