New Business - Program Management

Title: PM12 Reduction of Retainage for Conniston Community Middle

Recommendation:

I recommend the School Board approve Reduction of Retainage from 5% to 1% for Conniston Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

Conniston Community Middle School, Modernization Project #0541-8214

On Conniston Community Middle School, the Contractor, W.G. Mills, Inc., achieved Substantial Completion on August 6, 2004, and requested a Reduction of Retainage from 5% to 1%; the Architect and District staff recommends this reduction.

Financial Impact:
The financial impact to the Project's Budget is $0.00.

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
PM12 Conniston Retainage Backup.pdf
Data Panel 0541.pdf
PM12 Q&A 031605 Board Meeting.doc
Q&A PM12 attachment 01.pdf
Q&A PM12 attachment 02.pdf