Title: PM13 Reduction of Retainage for H.L. Watkins Middle Recommendation:
I recommend the School Board approve Reduction of Retainage from 10% to 5% for H.L. Watkins Middle School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: H.L. Watkins Middle School, Modernization Project #0121-8263
On H.L. Watkins Middle School, the Contractor, W.G. Mills, Inc., achieved Substantial Completion on January 8, 2005, for Phase 1 and requested a Reduction of Retainage from 10% to 5%; the Architect and District staff recommends this reduction.
Financial Impact:
The financial impact to the Project's Budget is $0.00.