Title: PM7 Reduction of Retainage for U.B. Kinsey

Recommendation:

I recommend the School Board approve Reduction of Retainage from 10% to 1% for U.B. Kinsey Elementary School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

 

U.B. Kinsey Elementary School Modernization Project #0361-8265 

 

Description: On U.B. Kinsey Elementary School, the Contractor, C.R. Klewin, achieved Substantial Completion on August 9, 2005, and requested a Reduction in Retainage from 10% to 1%.  The District staff recommends this reduction.

Financial Impact:

The financial impact to the Project's Budget is $0.00.

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
PM7 Backup.pdf
PM7 Site Plan.pdf
PM7 Data Panel.pdf