						 Title: PM10 Project Modifications for Forest Hill Community High Recommendation: 
I recommend the School Board approve Project Modifications in the amount of $353,827.00 for Forest Hill Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description:   
Forest Hill Community High School – Modernization Project #0581-8215 
   
This project modification contains the following item: 
  
§        COPR #3 in the amount of $353,827.00 
§        Description: Hurricane Frances and Jeanne repairs. 
§        Cause: School District Requested. 
§        Justification: Repairs required for safety and occupancy caused by Hurricane Frances and Jeanne which were not the responsibility of the Construction Manager.  
Financial Impact: 
The financial impact to the Project's Budget is $353,827.00. 
  
The source of funds is Hurricane Contingency fund for Hurricanes Frances and Jeanne.  