						 Title: PM1 Project Modifications for Wellington Area Middle Recommendation: 
I recommend the School Board ratify Project Modifications in the amount of $46,462.50 for Wellington Area Middle School (02-JJ), New School Construction Project, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description:   
Wellington Area Middle School (02-JJ) – New School Construction Project #3371‑8290 
  
 
This project modification contains the following item: 
  
- CCD #1 in the amount of $46,462.50
 
- Description:  Removal of unsuitable soils (muck) materials from areas of the building pad of the facility.
 
- Cause: Unforeseen Condition
 
- Justification: The soils report did not provide a boring in this location.  The Geotechnical Report provided borings at a random grid pattern throughout the project.
   
Financial Impact: 
The financial impact to the Project's Budget is $46,462.50. 
  
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.  