Title: PM1 Project Modifications for Wellington Area Middle Recommendation:
I recommend the School Board ratify Project Modifications in the amount of $46,462.50 for Wellington Area Middle School (02-JJ), New School Construction Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
Wellington Area Middle School (02-JJ) – New School Construction Project #3371‑8290
This project modification contains the following item:
- CCD #1 in the amount of $46,462.50
- Description: Removal of unsuitable soils (muck) materials from areas of the building pad of the facility.
- Cause: Unforeseen Condition
- Justification: The soils report did not provide a boring in this location. The Geotechnical Report provided borings at a random grid pattern throughout the project.
Financial Impact:
The financial impact to the Project's Budget is $46,462.50.
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
PM1 Backup.pdf
PM1 Site Plan.pdf
|