New Business - Program Management

Title: PM3 Project Modifications for Forest Hill Community High

Recommendation:

I recommend the School Board approve Project Modifications in the amount of $353,827.00 for Forest Hill Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

 

Forest Hill Community High School – Modernization Project #0581-8215

 

This project modification contains the following item:

  

§       COPR #3 in the amount of $353,827.00

§       Description: Hurricane Frances and Jeanne repairs.

§       Cause: School District Requested.

§       Justification: Repairs required for safety and occupancy caused by Hurricane Frances and Jeanne which were not the responsibility of the Construction Manager.

Financial Impact:

The financial impact to the Project's Budget is $353,827.00.

 

The source of funds is Hurricane Contingency fund for Hurricanes Frances and Jeanne. Ninty percent of all eligible costs are expected to reimbursed by FEMA. 

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
PM3 Backup.pdf
PM3 Site Plan.pdf
PM3 Data Panel.pdf