Title: CP4 Amend the CM Agmnt for Rolling Green ES

Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase II Final Guaranteed Maximum Price (GMP), in the amount of $20,533,878. to C.R. Klewin Southeast, Inc. for Construction Management at Risk Services for Rolling Green ES Modernization/Replacement, Project No.0781-7508.

Description:

Construction Management Services required for modernization/replacement of the existing Pre K-5 facility in accordance with the Board adopted Five-Year Capital Plan and the educational specifications approved by the Board on January 19, 2005 (amended by a memorandum to the Board on May 23, 2005).

Approved Budget: $19,755,650.

Construction Type: Tilt-wall

No. of Stories: Two

Gross Square Feet: 109,732 (New) 30,228 (Old)

Total 139,960

Cost Per Square Foot: $151.

Total Student Stations: 1026

Cost Per Student Station: $20,573.

Minority Participation: 9.05%

 

Preconstruction Fee: $139,764.

Phase I GMP (Demolition): $434,677.

Phase II Final GMP: $20,533,878.

Total Construction Cost: $21,108,319.

 

Financial Impact:
The financial impact is $20,533,878. The source of funds is the corresponding Capital Projects Budget. Additionally $1,352,669. will come from Restricted Reserve.  The District will provide Builder's Risk insurance for this phase of the project at a total cost of $151,951.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)

Joseph M. Sanches

Attachments (list):
beneficialinterest crklewin.pdf
ppe.c.r.klewin.pdf
datapanel.Rolling Green ES.pdf
siteplan.rollingreenes.pdf
Q&ACP4.doc
Q&ACP4.doc

spacer graphic