Title: CP5 Amend the CM Agmnt for Village Acad Secondary Level

Recommendation:
I recommend the School Board approve an Amendment to the Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase I Final Guaranteed Maximum Price (GMP), for construction in the amount of $14,628,180. to Suffolk Construction, Inc. for Construction Management at Risk Services for Village Academy Secondary Level, Project No.2811-8271.

Description:

Purchasing/Construction: CP5 Amend the CM Agmnt for Village Acad Secondary Level

Construction Management at Risk Services for construction of middle and high school classroom additions in accordance with the Board adopted Five-Year Capital Plan and the educational specifications approved by the Board on November 8, 2004 (amended by a memorandum to the Board on August 10, 2005).  To save on cost the GMP includes the shell of the high school spaces, but excludes the interior buildout which can be completed with minimal impact to the school at a later date.

Approved Budget: $14,333,250.  

Construction Type: Tiltwall  

No. of Stories: three  

Gross Square Feet: 85,000 

Cost Per Square Foot: $173. 

Total Student Stations: 1382  (758 New, 624 Existing)

Cost Per Student Station: $10,638.  

 

Preconstruction Fee: $73,220.  

Phase I Final GMP: $14,628,180.  

Total Construction Cost: $14,701,400.

Financial Impact:
The financial impact is $14,628,180. The source of funds is $68,982. from Capital Contingency, and the remaining budget of $14,333,250. will be funded from the corresponding Capital Projects Budget in both FY2006 and FY2007 ($6,433,501. FY07).The District will provide Builder's Risk insurance for this phase of the project at a total cost of $108,249.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us) 

Joseph M. Sanches

Attachments (list):
beneficialinterest.suffolk.pdf
ppe.suffolkconstruction.pdf
datapanel.villageacademy.pdf
siteplan.villageacademy.pdf
Q&ACP5.doc
Q&ACP5.doc

spacer graphic