						 Title: PM3 Project Modifications for Omni Middle Recommendation: 
I recommend the School Board ratify Project Modifications in the amount of $2,118.00 for Omni Middle School, HVAC Replacement Project, and authorize the Chairman and Superintendent to execute all related contract documents.
 
   
Description:   
Omni Middle School – HVAC Replacement Project #1991-8222 
  
This project modification contains the following item: 
  
- CCD #16 in the amount of $2,118.00. 
 - Description:  Install a new gas valve at the north side of the J Building. 
 - Cause:  School District Requested. 
 - Justification: This valve was removed and abandoned and was required to be reinstalled with a new valve, per code requirements.
   
Financial Impact: 
The financial impact to the Project's Budget is $2,118.00. 
  
The source of funds is Minor Projects.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches 
Attachments (list): 
PM3 Backup.pdf 
PM3 Site Plan.pdf 
PM3 Data Panel.pdf 
PM3 Omni MS Board  Report.pdf 
						 
					 |