Indian Ridge Replacement (Project #2411-8386) and CEP Alternative Education School (Project # 0842-7516)
This project modification contains the following item:
COPR #1: Adjust Contract Time Only.
Description: Modify the Construction Completion deadlines to become:
A) Indian Ridge Replacement School:
Substantial Completion: November 2, 2006.
Final Completion: January 31, 2007
Previous dates were:
Substantial Completion: July 1, 2006
Final Completion: August 1, 2006.
B) CEP Alternative Education Facility:
Substantial Completion: December 1, 2006.
Final Completion: March 1, 2007
Previous dates were:
Substantial Completion: December 1, 2005.
Final Completion: January 1, 2006.
C) This COPR resolves all project time duration issues through May 4, 2006. This COPR supersedes all documents (including contract documents) that referenced or indicated a start or completion date or a time duration for the project. This COPR further resolves all known issues through May 4, 2006 caused by unforeseen conditions and/or additional work requested by the Owner regarding the project schedule.
Cause - There is a difference of opinion between the parties as to the project Commencement, Substantial Completion and Final Completion dates. Also, unforeseen conditions and owner requests to date have impacted the schedule.
Justification - The dates must be adjusted in order to establish timeframes for completion, so that accountability can be restored, and so that the School District can plan for occupancy.