- On January 25, 2006 the School Board approved the Ground Lease and Cooperative Agreement for 03-Y. (See Exhibit “A”)
  
  
- Following the School Board’s approval of the agreements the following changes occurred:
  
         The funding of the construction of 03-Y 
          must be out of non-COPS Capital 
          revenue sources. 
  
          The surface water will remain on-site 
           instead of a two acre area off-site that  
           reduces FAU’s credit toward construction 
           and reduces the School District’s 
           contribution from $2,765,000.00 to 
           $2,475,000.00. 
                   
           The School Board and FAU will work 
           exclusively together to create a 
           curriculum that incorporates the Florida 
           Department of Education K-5 SSS 
           and the Palm Beach County School 
           District goals and key results through 
           environmental themes that focus on  
           content and technology for the 
           achievement of all students. 
  
- All documents must be fully executed by the School Board prior to August 1, 2006 or FAU is obligated to return the deed and conservation easement to the FAU Foundation.
   |