Title: PM4 Project Modifications for Congress Middle School

Recommendation:

I recommend the School Board approve Project Modifications in the amount of $57,135.00 for Congress Middle School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

Congress Middle School – Modernization Project #1581-8339

  

This project modification contains the following item:

 

§        Additional Architectural Services in the amount of $17,135.00.

§        Description: Provide additional services to modify the drawings that serve to implement modifications and alterations to the main circulation driveway connecting the existing main entry driveway, the existing bus drop-off, and the new parent drop-off loop for the new Congress Middle School.

§        Cause: School District Requested

§        Justification:  The realignment is necessary because a building at the existing school previously scheduled for partial demolition will be retained.  This building will be needed for the Barton Elementary School temporary occupancy.  The partial demolition of the building would have permitted the original, final, design of the drive to be constructed.

§        Estimated Construction Cost is $40,000.00

Financial Impact:

The financial impact to the Project's Budget is $57,135.00.

 

The source of funds is the FY2007 Project Budget.