I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Phase 1 Guaranteed Maximum Price (GMP) for Site Development and Underground Utility construction in the amount of $12,011,523 to James B. Pirtle Construction Company for Palm Beach Gardens High School, Project No. 1371-7506. and authorize the Superintendent and Board Chairman to sign all required documents.

Description:

This project will consist of Construction Management at Risk services required for phased construction to replace the existing school with a 2,560 student station facility.  Construction includes replacement of all existing structures including the stadium facility, athletic and practice fields.

 

Approved Budget: $62,912,964

Construction Type: Tilt Wall

No. of Stories: Three

Gross Square Feet: 402,540

Budgeted Construction Cost/Gross Square Foot: $156.28

Total Student Stations: 2,560

Budgeted Construction Cost/Student Station: $24,575

 

Preconstruction Fee: $296,941

Phase I GMP: $12,011,523

Total: $12,298,909

Financial Impact:
The financial impact is $12,011,523. The source of funds is the corresponding Capital Projects Budget. The District will provide Builder's Risk insurance for this phase of the project at a total cost of $88,885.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)

Joseph M. Sanches

Attachments (list):
beneficiainterest. James B. Pirtle Construction.pdf
ppe.James B. Pirtle Construction.pdf
datapanel.Palm Beach Gardens HS.pdf
siteplan.Palm Beach Gardens HS.pdf

spacer graphic