Architectural design services required for development of completed design documents for the construction of an approximately 176,803 GSF, 1,439 student station (1,200 student Program Capacity) replacement elementary school in accordance educational specifications approved by the Board on July 19, 2006. The existing school will remain operational during construction of the replacement school.
Approved Tentative Budget for Planning and Design: $2,028,864*
Approved Tentative Budget for Construction: $31,146,171*
Budgeted Construction Cost per GSF: $176
*Tentative budget for FY07 was approved by the Board on July 26, 2006.
Fees for Basic Services:$1,415,000
Off-site Civil Design: $65,000 (Not to Exceed)
Funds Available For:
Additional Services: $141,500
Reimbursable Expenses: $70,750
Total Contract Award: $1,692,250
Nine (9) firms responded to the RFP. Four (4) firms were shortlisted. The final ranking of the Selection Committee is as follows:
(1) BRPH Architects and Engineers
(2) Schenkel Shultz
(3) PGAL
(4) Acai & Associates (Hispanic)