						 Title: CP3-Amend the CM Agmnt for Barton ES Recommendation: 
I recommend the School Board approve the Phase II Final GMP to the Construction Management at Risk Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the  Phase II Final Guaranteed Maximum Price (GMP), for construction, in the amount of $26,042,304. to W.G. Mills, Inc. for Construction Management at Risk Services for Barton ES Modernization/Replacement, Project No.0741-7501. 
Description: Construction Management at Risk Services required for modernization of a 1107 student stations (964 student Program Capacity) elementary school in accordance with the educational specifications approved by the Board on January 19, 2005 (amended by memorandum to Board on May 23, 2005). 
  
Approved Construction Budget: $17,879,250 
  
Construction Type: Tilt-Wall 
No. of Stories: 2 
Gross Square Feet:139,042 
Construction Cost Per Square Foot: $190 
Total Student Stations: 1107 
Construction Cost Per Student Station: $23,894 
Minority Participation: 15% 
  
Preconstruction Fee:                                       $169,075    
Phase I GMP:                                                 $740,004  
Phase II Final GMP:                                    $26,042,304          Total Construction Cost:                             $26,451,383    
Financial Impact: 
The financial impact is $26,451,383. The source of funds is the corresponding Capital Projects Budget. The District will provide Builder's Risk insurance for this phase of the project at a total cost of $132,306. 
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us)  Joseph M. Sanches 
Attachments (list): 
beneficialinterest w g mills.pdf 
ppe-W.G. Mills.pdf 
educationaspecs.Barton ES.pdf 
datapanels.Barton ES.pdf 
siteplan.bartones.pdf 
						 
					 |