Title: PM11 Project Modifications for Wellington Area Middle Recommendation:
I recommend the School Board ratify Project Modifications for the addition of seven (7) consecutive calendar days and the amount of $8,677.24 for Wellington Area Middle School (02-JJ), New School Construction Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
Wellington Area Middle School (02-JJ) – New School Construction Project #3371‑ 8290
This project modification contains the following item:
CCD #1 in the amount of $8,677.24 and the addition of seven (7) consecutive calendar days.
- Description: Extend contract time due to Hurricane Wilma.
- Cause: Unforeseen Conditions.
- Justification: Hurricane “Wilma” created a disruption in all of the construction process. Damage to the overall site was minimal, as a result of preparation. Flooding, fuel shortages and the inability of the work force to reach the site were critical.
Financial Impact:
The financial impact to the Project's Budget is $8,677.24.
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
PM11 Wellington Area MS Backup.pdf
PM11 Wellington Area MS Site Plan.pdf
PM11 Wellintgon Area MS CSR.pdf
PM11 Wellington Area MS Facility List.pdf
|