Construction Management at Risk services required for construction of an approximately 176,800 GSF, 1440 student station replacement K-5 elementary school in accordance with the Educational Specifications approved by the Board on July 19, 2006.
Approved Budget for Construction: $31,000,000.00
Construction Type: TBD during Pre-Construction Phase
No. of Stories: TBD during Pre-Construction Phase
Gross Square Feet: 176,800
Budgeted Construction Cost/Gross Square Foot: $175.
Total Student Stations: 1440
Budgeted Construction Cost/Student Station: $21,528.
Preconstruction Phase Fee:
Fees: $255,460.
Reimbursable Expenses: $92,850.
Total: $348,310.
Eight (8) firms responded to the RFP and three (3) firms were shortlisted. The final ranking of the Selection Committee is as follows:
1. W.G. Mills
2. Moss & Associates, Inc.
3. The Weitz Company I, Inc.
Minority Participation: 15%