Title: PM3 Project Modifications for Royal Palm Recommendation:
I recommend the School Board ratify Project Modifications for the addition of 262 consecutive calendar days and the amount of $30,000.00 for Royal Palm School, Additions & HVAC Project #1801-8357, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
Royal Palm School – Additions & HVAC Project #1801-8357
This project modification contains the following item:
- CCD #2 in the amount of $30,000.00 for the addition of 262 consecutive calendar days.
- Description: Relocate chiller plant
- Cause: School District Requested.
- Justification: This relocation was necessary to better accommodate the replacement school, in lieu of the previous alterations and additions.
Financial Impact:
The financial impact to the Project's Budget is $30,000.00
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.