Construction Management at Risk services required for Preconstruction Phase Services including design review and recommendation to establish the Guarantee Maximum Price for construction of a 119,668 gross square foot, 745 student station K-5 replacement school with core facilities to accommodate 960 students. Construction will be in accordance with permitted design documents and Educational Specifications approved by the Board on May 17, 2006.
 
Estimated Budget for Construction: $22,475,056.
 
Construction Type: TBD during Pre-Construction Phase 
No. of Stories: TBD during Pre-Construction Phase 
Gross Square Feet: 119,668
Total Student Stations: 745 
 
Preconstruction Phase Service Fee: $99,395.
Reimbursable Expenses: $58,000.
Total Contract Award: $157,395.
 
Eight (8) firms responded to the RFP and three (3) firms were shortlisted.  The final ranking of the Selection Committee is as follows: 
 
1. James B. Pirtle Construction Co., Inc.
2. C.R. Klewin Southeast, Inc.
3. Heery International, Inc.
 
Minority Participation: 15%