						 Title: PM1 Project Modifications for Boca Raton Middle Recommendation: 
I recommend the School Board approve Project Modifications in the amount of $109,975.00 for the Boca Raton Community Middle School, Modernization Project #1491-8379, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description:   
Boca Raton Community Middle School – Modernization Project #1491-8379 
   
This project modification contains the following item: 
  
- Additional Architectural Services in the amount of $109,975.00 
 - Description:  The A/E will provide contract documents to upgrade the baseball field to accommodate both the high school and middle school.  The upgrades include a concession/restroom/press-box building, an expanded PE storage building, ball field lighting, batting cages, enhanced dugouts, scoreboard, flag pole, warm-up mounds, and a public address system.  The documents will also include the design for future lighting of the track/soccer area, basketball courts, and upgrading the turf of the soccer field. 
 - Cause:  School District Requested 
 - Justification:  The baseball field at the middle school will be the home field for both the middle school and high school. 
 - Construction costs are estimated to be $1,000,000.
   
Financial Impact: 
The Financial Impact to the Project’s Budget is $109,975.00. 
  
The source of funds is Capital Contingency.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches  
Attachments (list): 
Boca Raton MS Budget History.pdf 
Boca Raton MS Site Plan.pdf 
Boca Raton MS Data Panel.pdf 
Boca Raton MS CSR Analysis.pdf 
Boca Raton MS Facility List.pdf 
Q&APM1.doc 
						 
					 |