E-Agenda: Paperless Meeting System
Back to Agendaspacer graphic
 

New Business - Program Management

Title: PM1 Project Modifications for Boca Raton Middle

Recommendation:

I recommend the School Board approve Project Modifications in the amount of $109,975.00 for the Boca Raton Community Middle School, Modernization Project #1491-8379, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

 

Boca Raton Community Middle School – Modernization Project #1491-8379

  

This project modification contains the following item:

 

  • Additional Architectural Services in the amount of $109,975.00
  • Description:  The A/E will provide contract documents to upgrade the baseball field to accommodate both the high school and middle school.  The upgrades include a concession/restroom/press-box building, an expanded PE storage building, ball field lighting, batting cages, enhanced dugouts, scoreboard, flag pole, warm-up mounds, and a public address system.  The documents will also include the design for future lighting of the track/soccer area, basketball courts, and upgrading the turf of the soccer field.
  • Cause:  School District Requested
  • Justification:  The baseball field at the middle school will be the home field for both the middle school and high school.
  • Construction costs are estimated to be $1,000,000.

Financial Impact:

The Financial Impact to the Project’s Budget is $109,975.00.

 

The source of funds is Capital Contingency.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
Boca Raton MS Budget History.pdf
Boca Raton MS Site Plan.pdf
Boca Raton MS Data Panel.pdf
Boca Raton MS CSR Analysis.pdf
Boca Raton MS Facility List.pdf
Q&APM1.doc

spacer graphic