| 
						 Title: PM6 Project Modifications for Palm Springs Elementary Recommendation: 
I recommend the School Board ratify Project Modifications in the amount of $268,657.00 for Palm Springs Elementary School, Modernization Project #0651-8262, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description: Palm Springs Elementary School – Modernization Project #0651-8262 
This project modification contains the following items: 
Item #1
- CCD #4 (Item #1) in the amount of $60,000.00.
 
- Description: Field supervision to hurricane remediation.
 
- Cause: Unforeseen Conditions.
 
- Justification: Construction supervision for hurricane remediation work.
  
 
- CCD #4 (Item #2) in the amount of $8,600.00.
 
- Description: Labor time associated with hurricane repair process.
 
- Cause: Unforeseen Conditions.
 
- Justification: Construction field labor for hurricane repair work.
  
 
- CCD #4 (Item #3) in the amount of $5,000.00
 
- Description: Construction carpentry allocated for hurricane repair work.
 
- Cause: Unforeseen Conditions.
 
- Justification: Construction field labor for hurricane repair work.
  
 
- CCD #4 (Item #4) in the amount of $1,500.00.
 
- Description: Material supplies for hurricane repairs
 
- Cause: Unforeseen Conditions.
 
- Justification: Construction materials needed for hurricane damage.
  
 
- CCD #4 (Item #5) in the amount of $1,843.00
 
- Description: Landscaping clean-up and repair.
 
- Cause: Unforeseen Conditions.
 
- Justification: Landscaping clean-up and repair needed after hurricane damage.
  
 
- CCD #4 (Item #6) in the amount of $2,000.00
 
- Description: Fence repair and replacement.
 
- Cause: Unforeseen Conditions.
 
- Justification: Fence repair and replacement needed after hurricane damages.
  
 
- CCD #4 (Item #7) in the amount of $2,500.00
 
- Description: Cost for re-cleaning and waxing
 
- Cause: Unforeseen Conditions.
 
- Justification: Cost for re-cleaning and re-waxing flooring damaged by hurricane.
  
 
- CCD #4 (Item #8) in the amount of $18,275.00
 
- Description: Cabinetry replacement and reinstallation
 
- Cause: Unforeseen Conditions.
 
- Justification: Cabinetry repair and replacement needed at hurricane damaged areas.
  
 
- CCD #4 (Item #9) in the amount of $945.00
 
- Description: Cost for repairing damaged door
 
- Cause: Unforeseen Conditions.
 
- Justification: Repair needed after hurricane damages.
  
 
- CCD #4 (Item #10) in the amount of $5,428.00
 
- Description: Cost for replacing damaged VCT flooring
 
- Cause: Unforeseen Conditions.
 
- Justification: Replacement of damaged VCT flooring at areas associated with hurricane damage.
  
 
- CCD #4 (Item #11) in the amount of $12,006.00
 
- Description: Drywall replacement and patchwork.
 
- Cause: Unforeseen Conditions.
 
- Justification: Drywall repair and replacement needed at hurricane damaged areas.
  
 
- CCD #4 (Item #12) in the amount of $4,212.00
 
- Description: Painting of repaired drywall areas.
 
- Cause: Unforeseen Conditions.
 
- Justification: Cost for painting required drywall areas associated with hurricane damages.
  
 
 
 
 
- CCD #4 (Item #13) in the amount of $1,932.00
 
- Description: Cost for acoustical ceiling tile material replacement.
 
- Cause: Unforeseen Conditions.
 
- Justification: Replacement material for hurricane damaged acoustical ceiling tile.
  
 
- CCD #4 (Item #14) in the amount of $1,040.00
 
- Description: Sink reinstallation at hurricane damaged areas.
 
- Cause: Unforeseen Conditions.
 
- Justification: Reinstallation of sinks at repair and new cabinet areas associates with hurricane damage.
  
 
- CCD #4 (Item #15) in the amount of $3,900.00
 
- Description: Damaged light fixture replacement
 
- Cause: Unforeseen Conditions.
 
- Justification: Replacement of damaged light fixtures required at hurricane damaged areas.
  
 
- CCD #4 (Item #16) in the amount of $3,120.00
 
- Description: Marble window sill reinstallation.
 
- Cause: Unforeseen Conditions.
 
- Justification: Reinstallation of window sill required at repaired hurricane damaged areas.
  
 
- CCD #4 (Item #17) in the amount of $20,000.00
 
- Description: Cost for water damage assessment.
 
- Cause: Unforeseen Conditions.
 
- Justification: The Consultant provided damage assessment and remediation services at hurricane damaged areas.
  
 
- CCD #4 (Item #18) in the amount of $81,031.00
 
- Description: Cost for remediation services
 
- Cause: Unforeseen Conditions.
 
- Justification: Remediation serviced required for microbial cleaning at hurricane damaged areas.
  
 
- CCD #4 (Item #19) in the amount of $15,000.00
 
- Description: Cost for testing services
 
- Cause: Unforeseen Conditions.
 
- Justification: Testing of damaged areas required to determine water infiltration caused by hurricane.
  
 
- CCD #4 (Item #20) in the amount of $20,326.00
 
- Description: Turner Construction general, liability, subgard, bond, & O&P.
 
- Cause: Unforeseen Conditions.
 
- Justification: Added volume of work to Turner Construction.
   
Financial Impact: 
The Financial Impact to the Project’s Budget is $268,657.00. 
  
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches 
Attachments (list): 
Palm Springs ES Budget History.pdf 
Palm Springs ES Site Plan.pdf 
Palm Springs ES Data Panel.pdf 
Palm Springs ES CSR Anaylsis.pdf 
Palm Springs ES Facility List.pdf 
						 
					 |