Title: PM2 Project Modifications for John F. Kennedy Middle

Recommendation:

I recommend the School Board ratify Project Modifications in the amount of $384,226.68 for John F. Kennedy Middle School, Modernization Project #0201-7444, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

John F. Kennedy Middle School – Modernization Project #0201-7444

  

This project modification contains the following item:

 

  • CCD #5 in the amount of $384,226.68.
  • Description:  Muck removal and replacement fill
  • Cause:  Unforeseen Conditions
  • Justification: The GMP was based on the removal of 64,000 cy of muck. Excavation revealed that 88,848 cy of muck required removal.

Financial Impact:

The financial impact to the Project's Budget is $384,226.68.

 

The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
PM2 John F Kennedy MS Budget History.pdf
PM2 John F Kennedy MS Site Plan.pdf
PM2 John F Kennedy MS Data Panel.pdf