Title: CP-3 Amend the CM Agreement for Boynton Beach High Academy Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Final Guaranteed Maximum Price (GMP) for construction in the amount of $8,841,030 to Pavarini Construction Company for Boynton Beach Academy, Project No. 2361-8228 and authorize the Superintendent and Board Chairman to sign all required documents.
Description: Construction Management at Risk Services required for construction of new and renovated space for 129 student stations for academy students of vocal/chorus, dance and theatrical programs including a black box theater.
Estimated Construction Budget: $8,573,250
Number of Stories: One
Construction Type: Tilt-Wall
Gross Square Feet: 29,030
Budgeted Construction Cost per Gross Square Foot: $295
Building Cost per Gross Square Foot: $284
Student Stations: 129
Budgeted Construction Cost per Student Station: $66,425
Building Cost per Student Station: $63,850
Preconstruction Fee: $50,134
GMP: $8,841,030
Total Cost of Construction: $8,891,164
Building Cost: $8,236,746
Minority Participation: 25.6%
Financial Impact:
The financial impact is $8,906,454. The source of funds is the corresponding Capital Projects Budget. The District will provide Builder’s Risk insurance at a total cost of $65,424, which is included in the total financial impact.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)
Attachments (list):
Bene-Pavarini-BBHS.pdf
PPEGlossary+PAVARINI.pdf
EDSPEC BBHS Approved.pdf
DATAPANEL Boynton Beach High School.pdf
ConceptSitePlanBoynton Beach HS Academy.pdf
Orig Fully Executer Agreement Pavarini-BBHS Academy.pdf
GMP Amendment BBHS+Exh b+ Pavarini+legal+firm signatures.pdf
Checklist for 1st Amendment to CM@Risk Pavarini Boynton Beach High Academy.pdf
|