Construction Management @ Risk services required for Preconstruction Phase Services including design review and recommendation to establish the Guaranteed Maximum Price for construction of 76,185 GSF including instructional and support spaces, administration/student services, media center and a food services/dining area with stage. Total student stations will be increased from 502 to 1032. The existing administration building, kitchen/cafetorium and three classroom buildings will be demolished to accommodate the new construction. Students will remain on campus during construction. Construction will be in accordance with the Educational Specifications approved by the Board on September 20, 2006.
Estimated Budget for Construction: $13,500,000
Construction Type: To be determined during Preconstruction Phase.
No. of Stories: To be determined during Preconstruction Phase.
Gross Square Feet:76,583
Estimated Construction Cost/Gross Square Foot: $176
Total New Student Stations: 502
Estimated Construction Cost/Student Station: $26,892
Preconstruction Phase Fee: $103,671
Reimbursable Expenses: $ 40,100
Total: $143,771
Four (4) firms responded to the RFP of which three (3) were shortlisted. The final ranking of the Selection Committee is as follows:
(1) Suffolk Construction Company, Inc.
(2) C.R. Klewin SE., Inc.
(3) The Morganti Group
Minority Participation: 15%