Title: Amend the CM Agreement for Hagen Road ES Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Phase 1 Guaranteed Maximum Price (GMP) for construction in the amount of $1,185,000 to C.R. Klewin Southeast, Inc. for Hagen Road Elementary School Project No. 1421-8359 and authorize the Superintendent and Board Chairman to sign all required documents.
Description: Construction Management @ Risk Services required for Phase 1 construction for site and foundation of an approximately 120,656 sq ft, 889 student station replacement school, in accordance with the Educational Specifications approved by the Board on April 19, 2006.
Estimated Construction Budget: $ 19,410,113
Number of Stories: Two
Construction Type: Tilt-Wall
Gross Square Feet: 120,656
Budgeted Construction Cost per Gross Square Foot: $ 160
Actual Total Construction Cost per Gross Square Foot: $NA
Building Cost per Gross Square Foot (Div 3-16): $NA
Actual Building Cost per Gross Square foot (Div. 3-16): $NA
Student Stations: 889
Budgeted Construction Cost per Student Station: $21,833
Actual Construction Cost per Student Station (Div. 3-16): $NA
Preconstruction Fee: $230,922.
Phase 1 GMP: $1,185,000.
Total: $1,415,222.
Total Cost of Construction: $NA
Building Cost: $NA
Minority Sub-consultant Participation: 24%
Financial Impact:
The financial impact is $1,193,769 which includes the Phase 1 GMP of $1,185,000 and $8,769 for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Projects Budget.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)
Attachments (list):
Beneficial.pdf
PPE.pdf
edspecHagenRd.pdf
datapanel.pdf
siteplan.pdf
Agreement-Hagen Road ES CM.pdf
GMP AMENDMENT.pdf
GMP Proposal.pdf
Checklist.pdf
|