Title: Amend the CM Agreement for Palm Beach Gardens HS

Recommendation:

I recommend the School Board revise the construction budget to $104,981,784 and approve an Amendment to the Construction Management at Risk Agreement to establish the Phase 2 Guaranteed Maximum Price (GMP) for this project in the amount of $73,826,058. to James B. Pirtle Construction Company, Inc. for Palm Beach Gardens High Modernization, Project No: 1371-7506 and authorize the Superintendent and Board Chairman to sign all required documents. 

Description:

This project will consist of Construction Management at Risk services required for phased construction to replace the existing school with a 2,774 student station facility.  Construction includes replacement of all existing structures including the stadium facility, athletic and practice fields, in accordance with the Educational Specifications approved by the Board on July 20, 2005.  

 

Estimated Construction Budget: $75,895,946

                                             

Number of Stories: Three

Construction Type: Tilt Wall

 

Gross Square Feet: 402,540

Budgeted Construction Cost per Gross Square Foot: $189

Total Construction Cost per Gross Square Foot: $214

Building Cost per Gross Square Foot (Div 3-16): $187

 

Student Stations: 2560

Budgeted Construction Cost per Student Station: $29,647.

Total Construction Cost per Student Station: $33,646.

Building Cost per Student Station (Div. 3-16): $29,431.

 

Preconstruction Fee:                      $296,941.

Phase 1 GMP:                           $12,011,523.

Phase 2 GMP:                           $73,826,058.

 

Total Cost of Construction:       $86,134,522.

 

Building Cost (Div. 3-16):         $75,342,913.

 

Minority Sub-consultant Participation: 17%

Financial Impact:

The financial impact is an increase to the Project Budget of $10,238,576. and a commitment of $74,372,361. which includes the Phase 2 GMP of $73,826,048. and $546,313. for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Project Budget. The source of the additional funds is the Restricted Reserve.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)

Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)

Attachments (list):
Bene.pdf
PPE PIRTLE.pdf
PBGH ED SPEC.pdf
Chap4.1.pdf
PBGH Data Panel.pdf
Site plan.pdf

spacer graphic