Title: Amend the CM Agreement for West Boynton Area ES 03-Z

Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Phase 1 Guaranteed Maximum Price (GMP) for construction in the amount of $1,173,957 to W.G. Mills, Inc. for West Boynton Area Elementary School (03-Z), Project No. 0281-8843 and authorize the Superintendent and Board Chairman to sign all required documents.

Description:

Construction Management at Risk Services required for construction of a 122,966 GSF, 960 student station, K-5 elementary school. The new school shall be constructed to allow for the future addition of a 1,300 student capacity middle school facility. Construction of the elementary school will be in accordance with Educational Specifications approved by the Board April 19, 2006.

 

Estimated Construction Budget: $19,418,653

                                             

Number of Stories: Two

Construction Type: Tilt-Wall

 

Gross Square Feet: 122,966

Budgeted Construction Cost per Gross Square Foot: $158

Total Construction Cost per Gross Square Foot: NA

Building Cost per Gross Square Foot (Div 3-16): NA

 

Student Stations: 960

Budgeted Construction Cost per Student Station: $20,228

Total Construction Cost per Student Station: NA

Building Cost per Student Station(Div. 3-16): NA

 

Preconstruction Fee:                     $199,210.

Phase 1 GMP:                           $1,173,957.

Total:                                         $1,373,167.

 

Total Cost of Construction:     NA

 

Building Cost (Div. 3-16):      NA

 

Minority Sub-consultant Participation: 10.2 % (This is Phase 1 of a two phase project. The overall participation for this project is established at 15%.)  

Financial Impact:

The financial impact is a commitment of $1,173,957. The source of funds is the corresponding Capital Project Budget.

For Additional Information, contact:

Joseph M. Moore (moorej@palmbeach.k12.fl.us)

Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)

Attachments (list):
Bene.pdf
PPE WGMILLS.pdf
03_Z ED SPEC.pdf
Chap4.pdf
SITEPLAN.pdf

spacer graphic