Title: PM5 Boca Raton Community MS Project Modifications

Recommendation:

I recommend the School Board approve Project Modifications for the addition of one hundred seventy-four (174) non-compensable calendar days for Phase 1A/1B and three hundred five (305) non-compensable calendar days for Phase 2 of the Boca Raton Community Middle School CM@Risk Project #1491-8379 and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

This project modification contains the following items:

 

  • COPR #1 for the addition of  one hundred seventy-four (174) non-compensable calendar days for Phase 1A/1B substantial completion and an additional one hundred seventy-three (173) non-compensable calendar days for final completion.  It also includes three hundred five (305) non-compensable calendar days for Phase 2 completion.
  • Description:  Extend the Phase 1A and 1B project schedule by one hundred seventy-four (174) days.   Revise the Phase 1A and 1B substantial completion date from July 19, 2006 to January 9, 2007.  Extend the Phase 2 project schedule by three hundred five (305) days.  Revise the Phase 2 substantial completion date until April 30, 2008.
  • Cause:  Unforeseen Conditions
  • Justification:  The storms, vandalism and other contributing factors resulted in concurrent delays to the critical path of the project schedule.

Financial Impact:

The financial impact to the Project's Budget is $0.00

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
Boca Raton MS Backup.pdf
Boca Raton MS Budget History.pdf
Boca Raton MS Data Panel.pdf
Boca Raton MS Site Plan.pdf
Boca Raton MS CSR Anaylsis.pdf
Boca Raton MS Facility List.pdf

spacer graphic