Title: PM5 Boca Raton Community MS Project Modifications Recommendation:
I recommend the School Board approve Project Modifications for the addition of one hundred seventy-four (174) non-compensable calendar days for Phase 1A/1B and three hundred five (305) non-compensable calendar days for Phase 2 of the Boca Raton Community Middle School CM@Risk Project #1491-8379 and authorize the Chairman and Superintendent to execute all related contract documents.
Description: This project modification contains the following items:
- COPR #1 for the addition of one hundred seventy-four (174) non-compensable calendar days for Phase 1A/1B substantial completion and an additional one hundred seventy-three (173) non-compensable calendar days for final completion. It also includes three hundred five (305) non-compensable calendar days for Phase 2 completion.
- Description: Extend the Phase 1A and 1B project schedule by one hundred seventy-four (174) days. Revise the Phase 1A and 1B substantial completion date from July 19, 2006 to January 9, 2007. Extend the Phase 2 project schedule by three hundred five (305) days. Revise the Phase 2 substantial completion date until April 30, 2008.
- Cause: Unforeseen Conditions
- Justification: The storms, vandalism and other contributing factors resulted in concurrent delays to the critical path of the project schedule.
Financial Impact:
The financial impact to the Project's Budget is $0.00
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
Boca Raton MS Backup.pdf
Boca Raton MS Budget History.pdf
Boca Raton MS Data Panel.pdf
Boca Raton MS Site Plan.pdf
Boca Raton MS CSR Anaylsis.pdf
Boca Raton MS Facility List.pdf
|