Title: PM1 Emerald Cove MS Project Modifications Recommendation:
I recommend the School Board ratify Project Modifications in the amount of $331,329.72 for Emerald Cove Middle School (02-JJ), New School Project #3371-8290, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: This project modification contains the following items:
Item #1
- CCD #3 in the amount of $33,185.50
- Description: Add sound wall panels at the gymnasium Building #5.
- Cause: School District Requested.
- Justification: This project was a prototype re-use facility and the panels were not part of the original design scope.
Item #2
- CCD #4 in the amount of $15,596.00
- Description: Add galvanneal on all lockers and add 16 gauge slope tops
- Cause: School District Requested.
- Justification: This project was a prototype re-use facility and the described work was not part of the original design scope.
Item #3
CCD #5 in the NTE amount of $282,548.22
- Item #1 in the amount of $146,927.26
- Description: Provide irrigation and sod to Village of Wellington Olympic Park site.
- Cause: Outside Agency
- Justification: Village of Wellington required St. Augustine sod and irrigation system within retention areas that were not part of original scope.
- Item #2 in the amount of $39,454.46
- Description: Provide technology wiring and mounts.
- Cause: School District Requested
- Justification: Required to comply with revisions to School District technology criteria.
- Item #3 in the amount of $40,320.00
- Description: Revise the Florida Power & Light primary feed, utility transformer location and secondary feeds from the utility transformer to MDP in Building #6.
- Cause: Outside Agency
- Justification: Required by Florida Power & Light for electrical service to the school.
- Item #4 in the amount of $26,061.00
- Description: Off-site civil revisions, water main relocation, storm drainage, off-site paving and striping.
- Cause: Outside Agency
- Justification: Changes were made to satisfy the Village of Wellington plan review comments.
- Item #5 in the amount of $29,785.50
- Description: Interconnection of retention ponds.
- Cause: Outside Agency.
- Justification: Required by the Village of Wellington to tie off site retention ponds into school site retention area that led to Lake Worth Drainage Canal System.
Financial Impact:
The financial impact to the Project's Budget is $331,329.72
The source of funds is Capital Contingency.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
Emerald Cove MS Budget History.pdf
Emerald Cove MS Site Plan.pdf
Emerald Cove MS CSR Analysis.pdf
Emerald Cove MS Facility List.pdf
|