Title: PM3 Coral Sunset ES Project Modifications Recommendation:
I recommend the School Board ratify Project Modifications in the amount of $52,507.62 and for the addition of 283 non-compensable calendar days for Coral Sunset Elementary School, Classroom Addition Project #1811-8273, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: This project modification contains the following item:
- CCD #1 in the amount of $52,507.62 and 283 additional non-compensable days.
- Description: This CCD represents additional work as described in the attached summary titled Open PCO "Work Performed" Not Included in GMP Costs Requires Funding dated May 4, 2007.
- Cause: Unforeseen Conditions
- Justification: The Construction Manager, District staff, Architect and Engineers have reviewed the work items and agreed that they bring added value to the facility and have been fairly and reasonably priced. See attached. The additional non‑compensable days were required due to Unforeseen Conditions resulting from inaccurate as-builts, Hurricane Wilma, District Requested phasing changes, rain days, and added scope.
Financial Impact:
The financial impact to the Project's Budget is $52,507.62
The source of funds is Restricted Reserve.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
Coral Sunset ES Backup.pdf
Coral Sunset ES Budget History.pdf
Coral Sunset ES Data Panel.pdf
Coral Sunset ES Site Plan.pdf
Coral Sunset ES CSR Anaylsis.pdf
Coral Sunset ES Facility List.pdf
|