Title: PM1 Coral Reef ES Project Modifications Recommendation:
I recommend the School Board approve Project Modifications in the amount of $22,000.00 to Suffolk Construction for Coral Reef Elementary School, Class Size Reduction Project #2581-8950, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: This project modification contains the following item:
- COPR #1 in the amount of $22,000.00
- Description: Provide and install new two (2) inch conduit, cabling and intercom connections from Room 3-191 to the intercom system pull-box in Building #1.
- Cause: School District Requested
- Justification: There is interference in the intercom system that is a result of the intercom wire being installed in existing conduit with existing lines. Original construction documents showed this installation. The new conduit and wire will eliminate the interference.
Financial Impact:
The Financial Impact to the Project’s Budget is $22,000.00
The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
Coral Reef ES Budget History.pdf
Coral Reef ES Data Panel.pdf
Coral Reef ES CSR Analysis.pdf
Coral Reef ES Facility List.pdf
|