Construction Management @ Risk Services required for Preconstruction Phase Services including design review and recommendation to establish a Guaranteed Maximum Price for remodeling of existing classroom spaces to accommodate program requirements for a 325 student station, 30,351 gross square foot academy for an equine/pre-veterinarian program. Construction will be in accordance with the Educational Specifications approved by the Board on July 19, 2006.
Estimated Budget for Construction: $2,258,025 (Five Year Capital Plan)
Construction Type: To be determined during Preconstruction Phase
No. of Stories: To be determined during Preconstruction Phase.
Gross Square Feet: 30,351
Estimated Construction Cost/Gross Square Foot: $75.
Total New Student Stations: 325
Estimated Construction Cost/Student Station: $6948.
Preconstruction Phase Services Fee: $44,120.
Reimbursable Expenses: $9,650.
Total: $53,770.
Four (4) firms responded to the RFP of which three (3) were shortlisted. The final ranking of the Selection Committee is as follows:
(1) The Weitz Company, LLC
(2) Coastal Construction
(3) Hernandez Construction, LLC.
Minority Sub-contractor Participation: 21 %