Title: CP-4 Amend the CM Agreement for Allamanda Elementary School Replacement Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement to establish the Phase 2 Final Guaranteed Maximum Price (GMP) for construction in the amount of $21,299,768. to James B. Pirtle Construction Company, Inc., for Allamanda Elementary School Replacement Project No. 0101-8227 and authorize the Superintendent and Board Chairman to sign all required documents.
Description: Construction Management @ Risk Services required for Phase 2 Final construction of a 119,668 gross square foot, 745 student station K-5 replacement school with core facilities to accommodate 960 students, in accordance with the Educational Specifications approved by the Board on May 17, 2006.
Estimated Construction Budget: $22,475,056. (Five Year Capital Plan)
Number of Stories: Two
Construction Type: Tilt-Wall
Gross Square Feet: 119,668
Budgeted Total Construction Cost per Gross Square Foot: $188.
Total Actual Construction Cost per Gross Square Foot: $187. (Phase 1 & 2)
Building Only Cost per Gross Square Foot (Div 3-16): $164. (Phase 1 & 2)
Student Stations: 745
Budgeted Total Construction Cost per Student Station: $30,168.
Total Actual Construction Cost per Student Station: $30,110. (Phase 1 & 2)
Building Only Cost per Student Station (Div. 3-16): $26,322. (Phase 1 & 2)
Preconstruction Fee: $157,395.
Phase 1 GMP (Demolition): $975,118.
Phase 2 GMP (Final): $21,299,768.
Total Cost of Construction: $22,432,281.
Building Only Cost (Div. 3-16): $19,609,808.
Minority Sub-contractor Participation: 26 %
Financial Impact:
The financial impact is an increase to the project budget of $1,059,606. and a commitment of $21,457,387. which includes the Phase 2 Final GMP of $21,299,768. and $157,619. for the District provided Builder’s Risk Insurance. Of the above budget, $8,000,000. is available currently, and the remaining $13,457,387. will become available upon adoption of the FY2008-FY2012 5-Year Capital Plan ins September and the approval of the 2007E COPS issue in October 2007.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)
Attachments (list):
Beneficial.PDF
PPE.pdf
Facility Summary.pdf
Demographics.pdf
Data Panel.pdf
SITE ALLAMANDA.pdf
ExeAgreeFirstAmend.pdf
GMPProposal.pdf
SecondAmend.pdf
|