						 Title: CP-4 Amend the CM Agreement for Forest Park Elementary School Modernization Recommendation: 
I recommend the School Board revise the project budget to $31,655,184. and approve an  Amendment to the Construction Management at Risk Agreement to establish the Final Guaranteed Maximum Price (GMP) for construction in the amount of $23,405,047. to Moss & Associates, LLC for Forest Park Elementary School Modernization, Project No. 0831-8502 and authorize the Superintendent and Board Chairman to sign all required documents.  
Description: Construction Management @ Risk Services required for Phase 2 Final construction of a 798 student station elementary school with core facilities to accommodate 960 student stations.  Three classroom buildings will be retained from the existing facility, modernized to the extent necessary and incorporated into the construction for the 798 student station facility.  The construction process shall also incorporate consideration for the future addition of 188 student stations. Construction will be in accordance with the Educational Specifications approved by the Board on May 17, 2006. 
  
Estimated Construction Budget: $22,475,056. (Five Year Capital Plan) 
                                               
Number of Stories: Two 
Construction Type: Tilt-Wall 
  
Gross Square Feet: 106,647 
Budgeted Total Construction Cost per Gross Square Foot: $210.  
Total Actual Construction Cost per Gross Square Foot: $245. (Phase 1 & 2) 
Building Only Cost per Gross Square Foot (Div 3-16): $143.  (Phase 1 & 2) 
  
Student Stations: 798 
Budgeted Total Construction Cost per Student Station: $28,164. 
Total Actual Construction Cost per Student Station: $32,748. (Phase 1 & 2) 
Building Only Cost per Student Station (Div. 3-16): $19,156. (Phase 1 & 2) 
  
Preconstruction Fee:                   $200,406.       
GMP Phase 1:                          $2,527,258.  
GMP Phase 2 Final:               $23,405,047. 
  
Total Actual Cost of Construction:   $26,132,711.  
  
Total Building Only Cost (Div. 3-16): $15,286,873. (Phase 1 & 2) 
  Minority Sub-contractor Participation: 30%           
Financial Impact: 
The financial impact is an increase to the budget of $3,735,860. and a commitment of $23,578,244. which includes the GMP of $23,405,047. and $173,197. for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Projects Budget.    
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us)  
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)  
Attachments (list): 
Beneficial.pdf 
PPE.pdf 
Facility Summary.pdf 
CSA Table p3.pdf 
Data Panel.pdf 
Site Plan.pdf 
ExeAgreeAmend.pdf 
GMP Exh Z.pdf 
SecondAmendExhB.pdf 
Checklist.pdf 
						 
					 |