Construction Management at Risk services required for Phase 2 Final construction of a 145,828 GSF elementary school with related facilities and an adjacent 15,000 GSF facility to be utilized as an Environmental Studies Center by Florida Atlantic University. Construction shall be in accordance with the Educational Specifications approved by the Board on March 15, 2006. 
 
Estimated Construction Budget: $21,511,247. (Five Year Capital Plan)
                                              
Number of Stories: Two
Construction Type: Tilt-Wall
 
Gross Square Feet: 160,828 (145,828 GSF elementary school and 15,000 GSF Environmental 
Center)                                                            
Budgeted Construction Cost per Gross Square Foot: $134.
Total Construction Cost per Gross Square Foot: $189. 
Building Cost per Gross Square Foot (Div 3-16): $144.
 
Student Stations: 960
Budgeted Construction Cost per Student Station: $22,408.
Total Construction Cost per Student Station: $31,646, (Inclusive of Environmental Center)
Building Cost per Student Station (Div. 3-16): $24,164. (Inclusive of Environmental Center)
 
Preconstruction Fee:                          $322,185.
GMP Phase 1 (Site/Utilities):         $5,902,176.
GMP Phase 2 (Final):                   $24,156,084.
 
Total Cost of Construction:          $30,380,445.
 
Building Cost (Div. 3-16):           $23,197,626. (Phase 1 & 2)
 
Minority Sub-contractor Participation:16.2%