Title: CP-7 Amend the CM Agreement for Boca Raton High School Stadium Recommendation:
I recommend the School Board revise the project budget to $11,190,467. and approve an Amendment to the Construction Management at Risk Agreement to establish the Guaranteed Maximum Price (GMP) for construction in the amount of $9,694,880. to Balfour Beatty Construction, LLC, for Boca Raton High School Stadium, Project No: 0961-8275 and authorize the Superintendent and Board Chairman to sign all required documents.
Description: Construction Management @ Risk Services required for construction of an 11,450 GSF single story concession building, 4,000 seat stadium with press box and lighting, practice field, track, provision for a future aquatics facility and required parking, fencing and site work.
Estimated Construction Budget: $9,715,000. (Revised Five Year Capital Plan)
Number of Stories: NA
Construction Type: NA
Student Stations: NA
Budgeted Total Construction Cost per Student Station: $NA
Total Actual Construction Cost per Student Station (Div. 3-16): $NA
Building Only Cost per Student Station (Div. 3-16): $NA
Preconstruction Fee: $20,120.
GMP: $9,694,880.
Total Cost of Construction: $9,715,000.
Building Cost (Div. 3-16): $4,567,555.
Minority Sub-contractor Participation: 18%
Financial Impact:
The financial impact is an increase to the project budget of $6,961,817. and a commitment of $9,766,622. which includes the GMP of $9,694,880. and $71,742. for the District provided Builder’s Risk Insurance. The source of funds is the corresponding Capital Project Budget.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches (sanchesj@palmbeach.k12.fl.us)
Attachments (list):
Beneficial.pdf
PPE.pdf
Facility Statement.pdf
Data Panel.pdf
SitePlanBocaStadium.pdf
ExeAgr Centex.pdf
GMP Exh Z.pdf
AMENDMENT.pdf
Checklist.pdf
|