Title: Construction Management at Risk Agreement for Boynton HS Academy Recommendation:
I recommend the School Board approve an Agreement for Construction Management at Risk Services and Preconstruction Phase Fee in the amount of $50,134. to Pavarini Construction Company and authorize the Superintendent and Board Chairman to sign all required documents for Pre-Construction fees for Boynton Beach High School Academy, Project No. 2361-8228.
Description: Approved Construction Budget: $5,050,350.
Minority Participation: 15%
No. of Stories: One
Construction Type: Tilt-Wall
Gross Square Feet: 29,000
Student Stations: 129
Six (6) firms responded to the RFP of which three (3) were shortlisted. The final ranking of the Selection Committee is as follows:
(1)Pavarini Construction Company
(2)Kaufmanlynn, Inc. General Contractors
(3)C.R. Klewin Southeast, Inc.
Financial Impact:
The financial impact is $50,134. The source of funds is the project budget.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches
Attachments (list):
beneficialinterest.Pavarini.pdf
|