Title: Guaranteed Maximum Price for Limestone Creek ES Recommendation:
I recommend the School Board approve an Amendment to the Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase 3 Guaranteed Maximum Price (GMP), for Construction in the amount of $2,160,921. to C.R. Klewin Southeast, Inc. for Construction Management at Risk Services for Limestone Creek Elementary School Minor Renovation, Project No. 2031-8377.
Description: This project includes the classroom addition, a/c replacement brick repair and roof replacement.
Approved Construction Budget: $11,461,446.
No. of Stories: Building #1-Administration, one story, modernization, Building #3-Classroom, two story, new construction, Building #4-Administration, one story, modernization, Building #5- Multipurpose, one story, modernization
Construction Type: Tilt Wall and Concrete Masonry Units
Gross Square Feet: 106,000 (43,100 New, 62,900 Modernization) Construction Cost Per Gross Square Foot: $86. (excluding brick repair and roof replacement)
Total Additional Student Stations: 367
Construction Cost Per Student Station: $24,710. (excluding brick repair and roof replacement)
Preconstruction Fee: $67,982.
Phase I GMP: $5,278,836.
Phase II GMP: $3,721,628.
Phase III GMP: $2,160.921. (Brick Repair and Roof Replacement)
Total Construction Cost: $11,229,367.
Minority Participation: 21.1% (Total Project)
Financial Impact:
The financial impact is $2,168,454. The source of funds is the corresponding Capital Projects Budget. The District will provide Builder's Risk insurance for this phase of the project at a total cost of $16,047.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches
Attachments (list):
beneficialinterest.C.R.Klewin.pdf
periodicperformance.C.R.Klewin.pdf
data panel limestone creek es.pdf
siteplan.limestone creek es.pdf
phase III gmp.limestone creek es..pdf
|