						 Title: Guaranteed Maximum Price for Limestone Creek ES Recommendation: 
I recommend the School Board approve an Amendment to the Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase 3 Guaranteed Maximum Price (GMP), for Construction in the amount of $2,160,921. to C.R. Klewin Southeast, Inc. for Construction Management at Risk Services for Limestone Creek Elementary School Minor Renovation, Project No. 2031-8377.  
Description: This project includes the classroom addition, a/c replacement brick repair and roof replacement. 
  
Approved Construction Budget: $11,461,446.  
  
No. of Stories: Building #1-Administration, one story, modernization, Building #3-Classroom, two story, new construction, Building #4-Administration, one story, modernization, Building #5- Multipurpose, one story, modernization  
Construction Type: Tilt Wall and Concrete Masonry Units  
Gross Square Feet: 106,000 (43,100 New, 62,900 Modernization) Construction Cost Per Gross Square Foot: $86. (excluding brick repair and roof replacement) 
Total Additional Student Stations: 367  
Construction Cost Per Student Station: $24,710. (excluding brick repair and roof replacement) 
Preconstruction Fee: $67,982.  
Phase I GMP: $5,278,836. 
Phase II GMP: $3,721,628.  
Phase III GMP: $2,160.921. (Brick Repair and Roof Replacement)  
Total Construction Cost: $11,229,367.  
Minority Participation: 21.1% (Total Project)  
Financial Impact: 
The financial impact is $2,168,454. The source of funds is the corresponding Capital Projects Budget. The District will provide Builder's Risk insurance for this phase of the project at a total cost of $16,047.   
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) 
Joseph M. Sanches 
   
Attachments (list): 
beneficialinterest.C.R.Klewin.pdf 
periodicperformance.C.R.Klewin.pdf 
data panel limestone creek es.pdf 
siteplan.limestone creek es.pdf 
phase III gmp.limestone creek es..pdf 
						 
					 |