Title: PM13 Lake Worth Middle Project Modifications Recommendation:
I recommend the School Board ratify Project Modifications in the amount of $9,000.00 for Lake Worth Middle School, Classroom Addition Project #2131-8307, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: This project modification contains the following item:
§ CCD #2 in the amount of $9,000.00
§ Description: Civil engineering services involving permitting and coordination efforts with Outside Agency for on-site fire and potable water connections to existing utility, as well as modification and approval of the existing environmental resource permit.
§ Cause: Design Omission – Discovered during the permitting process.
§ Justification: Existing on-site utility is owned by Outside Agency.
§ Construction costs are estimated to be approximately $100,000.00.
Financial Impact:
The financial impact to the Project's Budget is $9,000.00.
The source of funds is the Capital Project Budget.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches
Attachments (list):
Lake Worth MS Budget History.pdf
Lake Worth MS Site Plan.pdf
Lake Worth MS Data Panel.pdf
Lake Worth MS CSR Chart.pdf
Lake Worth MS Facility List.pdf
|