Title: PM1 Retainage from 10% to 5% for Forest Hill

Recommendation:

I recommend the School Board approve Project Modifications for the addition of 208 non-compensable days and approve Reduction of Retainage from 10% to 5% for Forest Hill Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

Forest Hill Community High School – Modernization Project #0581-8215

  

Item #1
  • COPR #2 for the addition of 208 days.
  • Description: A non-compensable time extension of 208 days.
  • Cause:  School District Requested.
  • Justification:  Due to operational needs of the school, the phasing plan was revised causing delays in providing access to Media Center and completion of the auditorium.

Item #2

  • Description:  On Forest Hill Community High School, the Contractor, James A. Cummings, Inc., achieved Substantial Completion on August 13, 2004, and requested a Reduction of Retainage from 10% to 5%; the Architect and District staff recommends this reduction.

Financial Impact:

The financial impact to the Project's Budget is $0.00.

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches