Title: PM1 Retainage from 10% to 5% for Forest Hill Recommendation:
I recommend the School Board approve Project Modifications for the addition of 208 non-compensable days and approve Reduction of Retainage from 10% to 5% for Forest Hill Community High School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: Forest Hill Community High School – Modernization Project #0581-8215
Item #1
- COPR #2 for the addition of 208 days.
- Description: A non-compensable time extension of 208 days.
- Cause: School District Requested.
- Justification: Due to operational needs of the school, the phasing plan was revised causing delays in providing access to Media Center and completion of the auditorium.
Item #2
- Description: On Forest Hill Community High School, the Contractor, James A. Cummings, Inc., achieved Substantial Completion on August 13, 2004, and requested a Reduction of Retainage from 10% to 5%; the Architect and District staff recommends this reduction.
Financial Impact:
The financial impact to the Project's Budget is $0.00.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches