						 Title: CP4 Amend the CM Agmnt for Rolling Green ES Recommendation: 
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase 1 Guaranteed Maximum Price (GMP), for demolition in the amount of $434,677. to C.R. Klewin Southeast, Inc. for Construction Management at Risk Services for Rolling Green ES Modernization/Replacement, Project No.0781-7508.  
Description: Construction Management at Risk Services required for demolition of the existing facility with the exception of Buildings 3, 4, 5 and 9. 
Approved Budget: $15,828,437. 
Construction Type: Tilt-wall 
No. of Stories: Two 
Gross Square Feet: 101,244 (New) 24,343 (Old)  
Total 125,587 
Budgeted Construction Cost/Gross Square Foot: $126. 
Total Student Stations: 1026 
Budgeted Cost/Student Station: $15,427. 
  
Preconstruction Fee: $139,764. 
Phase I GMP (Demolition): $434,677. 
Total Construction Cost:$TBD.  
Financial Impact: 
The financial impact is $434,677. The source of funds is the corresponding Capital Projects Budget.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us)  
Joseph M. Sanches   
Attachments (list): 
beneficialinterest crklewin.pdf 
ppe.c.r.klewin.pdf 
siteplan rollinggreenes.pdf 
datapanel.Rolling Green ES.pdf 
						 
					 |