Title: CP4 Amend the CM Agmnt for Rolling Green ES Recommendation:
I recommend the School Board approve an Amendment to the Construction Management at Risk Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase 1 Guaranteed Maximum Price (GMP), for demolition in the amount of $434,677. to C.R. Klewin Southeast, Inc. for Construction Management at Risk Services for Rolling Green ES Modernization/Replacement, Project No.0781-7508.
Description: Construction Management at Risk Services required for demolition of the existing facility with the exception of Buildings 3, 4, 5 and 9.
Approved Budget: $15,828,437.
Construction Type: Tilt-wall
No. of Stories: Two
Gross Square Feet: 101,244 (New) 24,343 (Old)
Total 125,587
Budgeted Construction Cost/Gross Square Foot: $126.
Total Student Stations: 1026
Budgeted Cost/Student Station: $15,427.
Preconstruction Fee: $139,764.
Phase I GMP (Demolition): $434,677.
Total Construction Cost:$TBD.
Financial Impact:
The financial impact is $434,677. The source of funds is the corresponding Capital Projects Budget.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches
Attachments (list):
beneficialinterest crklewin.pdf
ppe.c.r.klewin.pdf
siteplan rollinggreenes.pdf
datapanel.Rolling Green ES.pdf
|