Title: PM8 Reduction of Retainage for Roosevelt Elementary

Recommendation:

I recommend the School Board approve Reduction of Retainage for Phase I from 5% to 0% and for Phase II from 10% to 5% for Roosevelt Elementary School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

 

Roosevelt Elementary School Modernization Project #0341-8260

 

Item #1

  • Description:  On Roosevelt Elementary School, the Contractor, James A. Cummings, Inc., achieved Phase I Substantial Completion on August 9, 2004, and requested a Reduction of Retainage from 5% to 0%:  The Architect and District staff recommends this reduction. 

Item #2:

  • Description:  On Roosevelt Elementary School, the Contractor, James A. Cummings, Inc., achieved Phase II Substantial Completion on September 15, 2005, and requested a Reduction of Retainage from 10% to 5%.  The Architect and District staff recommends this reduction.

Financial Impact:

The financial impact to the Project's Budget is $0.00.

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
PM8 Roosevelt ES Backup.pdf
PM8 Roosevelt ES Site Plan.pdf
PM8 Roosevelt ES Data Panel.pdf

spacer graphic