						 Title: PM8 Reduction of Retainage for Roosevelt Elementary Recommendation: 
I recommend the School Board approve Reduction of Retainage for Phase I from 5% to 0% and for Phase II from 10% to 5% for Roosevelt Elementary School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.  
Description: 
  
Roosevelt Elementary School – Modernization Project #0341-8260 
  
Item #1 
- Description:  On Roosevelt Elementary School, the Contractor, James A. Cummings, Inc., achieved Phase I Substantial Completion on August 9, 2004, and requested a Reduction of Retainage from 5% to 0%:  The Architect and District staff recommends this reduction. 
  
Item #2: 
- Description:  On Roosevelt Elementary School, the Contractor, James A. Cummings, Inc., achieved Phase II Substantial Completion on September 15, 2005, and requested a Reduction of Retainage from 10% to 5%.  The Architect and District staff recommends this reduction.
   
Financial Impact: 
The financial impact to the Project's Budget is $0.00.  
For Additional Information, contact: 
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches 
Attachments (list): 
PM8 Roosevelt ES Backup.pdf 
PM8 Roosevelt ES Site Plan.pdf 
PM8 Roosevelt ES Data Panel.pdf 
						 
					 |