Title: PM4 Retainage from 5% to 1% for H.L. Watkins Recommendation:
I recommend the School Board approve Reduction of Retainage from 5% to 1% for H.L. Watkins Middle School, Modernization Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description:
H.L. Watkins Middle School – Modernization Project #0121-8263
Description: Description: On H. L. Watkins Middle School, the Contractor, W. G. Mills, Inc., achieved Substantial Completion on September 8, 2005, and has requested a Reduction of Retainage from 5% to 1%; the Architect and District staff recommends this reduction.
Financial Impact:
The financial impact to the Project's Budget is $0.00.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches