Title: CP7 Guaranteed Maximum Price for Limestone Creek ES Recommendation:
I recommend the School Board approve an Amendment to the Agreement and authorize the Superintendent and Board Chairman to sign all required documents to establish the Phase I Guaranteed Maximum Price (GMP), for Construction in the amount of $5,278,836. to C.R. Klewin Southeast, Inc. for Construction Management at Risk Services for Limestone Creek Elementary School Addition, Project No. 2031-8377.
Description: This project will consist of Construction Management at Risk Services required for the construction of classroom additions and increased core facilities including administration, media center, multi-purpose rooms and dining. The student stations will increase from 597 to 964.
Approved Construction Budget: $6,849,746.
Minority Participation: 24%
No. of Stories: Building #1-Administration, one story, modernization, Building #3-Classroom, two story, new construction, Building #4-Administration, one story, modernization, Building #5-Multipurpose, one story, modernization
Construction Type: Tilt Wall and Concrete Masonry Units
Gross Square Feet: 106,000 (43,100 New, 62,900 Modernization)
Construction Cost Per Gross Square Foot: $64.62
Total Additional Student Stations: 367
Construction Cost Per Student Station: $18,664.16
Precon. Fee: $67,981.80
Phase I GMP: $5,278,836.
Total Construction Cost: $5,346,817.80
Financial Impact:
The financial impact is $5,278,836. The source of funds is the project budget. The District will provide the Builder's Risk Insurance at a cost of $39,063.39.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches
Attachments (list):
gmp2.crklewin.pdf
minorityparticipation2.crklewin.pdf
beneficialinterest crklewin.pdf
ratingsource.crklewin.pdf
siteplan.limestone creek.pdf
datapanel limestone creek.pdf
|