Title: PM4 Project Modifications for Watson B. Duncan Recommendation:
I recommend the School Board approve Project Modifications in the amount of $15,264.00 for Watson B. Duncan Middle School, HVAC Replacement Project, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: Watson B. Duncan Middle School, HVAC Replacement Project #1971-8222
This Project Modification contains the following items:
Item #1 • CCD #1 in the amount of $7,227.00 • Description: Upgrade electrical code violations, Building #4. • Cause: Unforeseen Condition • Justification: During the HVAC modifications electrical code violations were discovered.
Item #2 • CCD #2 in the amount of $2,387.00 • Description: Add piping for 2 roof drains in the chiller room. • Cause: Design Omission • Justification: The drawings indicated roof drains, but did not include the piping on the riser diagrams.
Item #3 • CCD #3 in the amount of $5,650.00 • Description: Add a 1000 amp breaker to the main switch gear. • Cause: Design Omission • Justification: The drawings indicated the breaker was 100 amps, a 1000 amp breaker is required.
Financial Impact:
The financial impact to the Project's Budget is $15,264.00. The source of funds is Minor Projects.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
PM4 Backup.pdf
PM4 Data Panel.pdf
PM4 Site Plan.pdf
Q&Apm4.doc
|