Title: PM2 Educational Specification for Palm Beach Gardens High Recommendation:
I recommend the School Board approve the Educational Specification for the modernization to Palm Beach Gardens High School, and authorize the Chairman and Superintendent to execute all related contract documents.
Description: 1. The construction of the modernization to Palm Beach Gardens High is scheduled to commence 2007 and be completed by 2009 according to the Board-adopted FY 2005 - FY 2009 Five-Year Plan.
2. The Educational Specification for modernization to Palm Beach Gardens High is consistent with the CSR facility lists and CSR Generic Educational Specifications approved by the Board on November 8, 2004.
3. Fifteen (15) additional ESE Resource Rooms were added to accommodate the existing ESOL and Reading programs at Palm Beach Gardens High as authorized by the Charter School District Waiver granted by the Florida Board of Education on January 21, 2003.
4. The "CSR FISH Capacity" of this school design would be 2,635 and the "Program Capacity" of this school design would be 2,500 students.
5. The Educational Specification reflects the use of academic houses to enable implementation of the "school-within-a-school" concept.
7. The Educational Specification was reviewed and approved by the principal.
Financial Impact:
Financial impact will be determined when construction contract is negotiated.
For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us) Joseph M. Sanches
Attachments (list):
PM2 Backup.pdf
PM2 Data Panel.pdf
Q&Apm2.doc
|