New Business - Program Management

Title: PM3 Project Modifications for Seminole Ridge High

Recommendation:
I recommend the School Board approve Project Modifications in the amount of $14,261.50 for Seminole Ridge High School, Construction Management at Risk Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

Seminole Ridge High School (02-NNN) – CM@Risk Project #3861-8292 

 

This project modification contains the following items:

 

Item #1

  • Additional Architectural Services in the amount of $6,534.00.
  • Description: Civil Engineering services to adapt entrances to final elevations of Seminole Pratt Road.
  • Cause: School District Requested.
  • Justification: Engineering services necessary to tie-in school entrance driveways to Pratt Whitney Road.
  • Construction costs are included in the GMP. 

Item #2

  • Additional Architectural Services in the amount of $7,727.50
  • Description: Civil Engineering services to locate and construct greenhouse (part of bio-tech academy), and observations and inspections associated with the required drainage and utilities of the Greenhouse.
  • Cause: School District Requested.
  • Justification: Engineering services necessary to construct the greenhouse.
  • Construction costs are included in the GMP.

Financial Impact:

The financial impact to the Project's Budget is $14,261.50.

 

The source of funds is the project budget as approved by the Board at the time of the Construction Contract Award.

For Additional Information, contact:
Joseph M. Moore (moorej@palmbeach.k12.fl.us)
Joseph M. Sanches

Attachments (list):
PM3 Backup.pdf
PM3 Site Plan.pdf
Q&APM3.doc