Title: PM6 Project Modification for Pierce Hammock

Recommendation:

I recommend the School Board approve Project Modification in the credit amount of ($215,835.64) for Pierce Hammock Elementary School (00-Q), Construction Management at Risk Project, and authorize the Chairman and Superintendent to execute all related contract documents.

Description:

Pierce Hammock Elementary School (00-Q) CM@Risk Project #2861-8257

 

This project modification contains the following item:

 

§         COPR #1 in the credit amount of ($215,835.64).

§         Description: Summary of unexpended funds to be returned from the construction manager's contract to the project budget:

o       Total Remaining Reimbursable items

$1,911.70

o       Construction Reimbursable General Conditions

$45,553.81

o       District Material Purchased by SDPBC

$3,118,871.47

o       Sales Tax Savings above goal

$37,101.20

o       Remaining Construction Contingency

$136,921.00

o       Total Remaining Reimbursable Items

$3,340,359.18

o       Deduct District Material Purchased by SDPBC

($3,118,871.47)

o       Deduct Funds Associated with CCA #037

($5,652.07)

o       Net Credit to SDPBC after DMP’s

($215,835.64)

  • Cause: School District Requested.
  • Justification: These funds are the remaining balances from allocated funds that were not expended. 

Financial Impact:

The financial impact to the Project's Budget is a credit of ($215,835.64).